Premier Health Miami Valley Hospital New Chiller Plant

Chiller Plant Relocation
Project Detail:

Cost $9,435,500

Size (3) 1,000-ton Chillers

Markets:

HEAPY Solutions designed, constructed, and managed a new 3,000-ton chilled water plant for Premier Health Miami Valley Hospital. The project included three (3) 1,000-ton chillers, pumps, new primary electric gear, large, chilled water piping, plant controls, construction of a new mechanical room, and geothermal injection wells.

Project Accomplishments:

HEAPY Solutions provided on-site quality assurance of installation, performance, and testing while managing project schedules, sequencing, daily logs, contract modifications, cost estimates, and RFI’s. HEAPY Solutions provided reports on project work activities, schedules, submittal tracking, and shutdown impact on hospital operations.

By installing high-efficiency chillers and reducing the number of chillers required to run during peak season from 10 chillers to 7, they improved the consumption of energy.  The installation of two additional injection wells allowed the hospital to return an additional 1600 GPM of water to the aquafer.  The chiller plant is now completely automated and has the ability to open and close valves with the push of a button.


Sustainable Support for Today and Tomorrow
HEAPY’s comprehensive services ensure exceptional system performance over the life of your building.
Chart Your Own Course
Our culture of growth and development empowers you to achieve your full potential.