Mercy Health Fairfield AHU 8 and 11 Replacement
HEAPY Solutions removed the existing air handling units 8 and 11 and replaced them with a new larger air handling unit 8 that serves both areas. Work also included removal of dual duct boxes and replacement with a VAV box with hot water reheat. Work included all material, installation, management, permitting, programming, and testing for an operational system.
HEAPY Solutions provided on-site quality assurance of installation, performance, and testing while managing project schedules, sequencing, daily logs, contract modifications, cost estimates and RFI’s. HEAPY Solutions provided reports on project work activities, schedules, submittal tracking and shutdown impact to hospital operations.
HEAPY Solutions maintained normal Emergency Department operation during HVAC replacement.