Financial Institution

Project Overview

Heapy provided commissioning services for fire suppression, heating, ventilating, air conditioning, electrical and technology systems associated with the data systems support infrastructure for the Bank and Vantiv tenant space at the Fifth Third Bank, CSC I and CSC II, Grand Rapids, Michigan site. Both sites were fully functional during all testing of new and existing systems with no outages.

Heapy commissioned the following building systems:
Chilled Water System
Air Handling Systems
Heating/Cooling Systems
Heat Pump Units
Automatic temperature controls system
Lighting Control Systems
Terminal Units
Main Distribution Switchgear
Emergency Generators
Emergency Distribution Switchgear
Paralleling Switchgear
Automatic Transfer Switches
Static Transfer Switches
Uninterruptable Power Systems
Battery Backup Systems
Battery Monitoring Systems

The projects had an estimated construction cost of $4.5 million.

Details:

COST
$4,500,000
SIZE
15,000 SF

Markets:

Thought Content

Planning for the New Normal
Plumbing Systems Re-Occupancy and Ongoing Operations

Your building may have been shut down these past many months due to WFH/COVID. Minimal use of your building’s water systems creates stagnant water in your plumbing system piping and equipment, which promotes the growth of Legionella and/or other biofilm-associated bacteria. This places your building occupants at risk when re-occupancy occurs. Now is the time to develop and implement a safe and effective Water Management Plan to protect your building occupants, maximizing their health and safety upon re-occupancy.

Read More